Power Construction Joint Stock Company (PC1) has announced the use of proceeds from the private placement as follows:
I. Result of public offering:
II. Report on the use of capital from the public offering:
- Total proceeds from the offering will be used for investing in Bao Lam 3 Hydropower project.
- Total amount has disbursed for the project until the reporting time: VND378,793,694,000.
- The remaining amount has not disbursed: 0 dongs
- The final payment date of the disbursement period: August 21, 2018
- Current project progress: Project progress has been fulfilled as planned. The project has finished and put into the generate electricity operation in December 2017.