No more time for delays to Long Thành Airport
Vietnamnews - 6/15/2022 4:16:46 PM
 (0 ratings. You must sign in to rate.)
To keep the Long Thành International Airport project on schedule, the Government has established an inter-disciplinary working team of officials from the transport and construction ministries and a deputy minister of transport will visit the construction site weekly to push the pace of the project.
 
These new measures were announced at a meeting held on Tuesday chaired by Deputy Prime Minister Lê Văn Thành, who is also head of the project's steering committee.
 
Thành said the steering committee will convene every month to review the progress of the project.
 
Minister of Transport Nguyễn Văn Thể said the project was on the right track and must not be delayed any further so that it can go into trial operation in early 2025.
 
The deputy prime minister also ordered Đồng Nai’s People’s Committee to complete land clearance and asked the authorities to build road and railway systems connecting the airport with localities.
 
At the next meeting, the transport ministry must report the results of a survey on the road from the airport to HCM City.
 
He also asked members of the Steering Committee to visit the site regularly and push the progress of the project, to make sure it is implemented in accordance with the report.
 
Despite having some positive progress since the site check on April 27 this year, ground levelling work hasn’t been up to expectations, the deputy prime minister said.
 
Transport minister Thể said ground levelling is an important task of the project and will affect other tasks if it is not completed, noting that it must be finished by July next year.
 
He added that a deputy minister has been assigned to the construction site to examine and accelerate the progress.
 
Covering more than 5,580 hectares, the Long Thành International Airport will spread across six communes in Long Thành District. Its construction has been divided into three phases. 
 
In the first phase, a runway and one passenger terminal, along with other supporting facilities, will be built to serve 25 million passengers and 1.2 million tonnes of cargo each year. This phase is scheduled to be completed in 2025.
 
The project started in 2021. Once fully completed in 2050, the airport will be able to handle 100 million passengers and 5 million tonnes of cargo annually.
 
Located 40km to the east of HCM City, the airport is expected to relieve overloading at the southern metropolis’s Tân Sơn Nhất International Airport, which is currently the largest in Việt Nam. VNS
 
Read original article here
 
Newer News
24/11 Fertiliser producers post record profits in Q3
20/11 CTD: Coteccons announces cash dividends following record profit
20/11 FPT and FutureTEC form exclusive partnership to drive digital growth in the Middle East
20/11 Young leadership mindset and SHB’s breakthrough journey in a new era
18/11 FOX: FPT Telecom to hold first extraordinary shareholders meeting after transfer
14/11 HSG: Hoa Sen Group to invest $38 million in construction materials distributor
13/11 HDB: HDBank well on course to hit 2025 profit targets
13/11 Việt Nam’s auto market surges 24%, VinFast sets new record
05/11 HVN: Vietnam Airlines launches direct flight connecting Hà Nội-Jakarta
04/11 CTD: Coteccons reports highest quarterly profit in 5 years
Older News
15/06 VIC: Automaker VinFast to open more than 50 stores in Europe
15/06 HVN: Vietnam Airlines proposes solutions for recovery
15/06 Việt Nam sees growth in garment exports in first five months
15/06 VNL: Announcement of the change of listing
15/06 REE: Decision on the change of listing
15/06 PDN: RECORD DATE FOR CASH DIVIDEND OF 2021
15/06 NTL: RECORD DATE FOR CASH DIVIDEND OF 2021
15/06 EVG: Notification insider transaction
15/06 LIX: RECORD DATE FOR CASH DIVIDEND OF 2021
15/06 BAF: Decision on the change of listing
 
Newsletter Signup
Top Stories
Stock market poised for boost in variety with new IPO wave
Financial market enters a new cycle of asset realignment
HDB: HDBank well on course to hit 2025 profit targets
Stock market realigns capital flows, long-term expectations
Việt Nam well positioned for breakthrough growth in 2026 as global investors renew confidence
Market Update
Last updated at 3:10:01 PM
VN-INDEX 1,684.32 +3.96/+0.24%
Real-time chart
Top 5 Actives
Top 5 Gainers
Top 5 Losers
My Favorite Quotes
Company Research
Type in the symbol above for thorough background information, key statistics and financial information.
Stock Sectors
We continuously improve our services, here are the latest updates...
Portfolio
Allow you to monitor a customised group of securities. You can set up multiple Portfolios to help you better manage your investments.
Trigger Alerts
Get up-to-date alerts delivered directly to your email address.
Stock Screener
Allow you to filter the market and find exactly what sort of company you are looking for.
Live Terminal
Get instant access to FREE REAL-TIME streaming quotes for hundreds of stocks from HOSE, HNX and UPCOM exchanges.