No more time for delays to Long Thành Airport
Vietnamnews - 6/15/2022 4:16:46 PM
 (0 ratings. You must sign in to rate.)
To keep the Long Thành International Airport project on schedule, the Government has established an inter-disciplinary working team of officials from the transport and construction ministries and a deputy minister of transport will visit the construction site weekly to push the pace of the project.
 
These new measures were announced at a meeting held on Tuesday chaired by Deputy Prime Minister Lê Văn Thành, who is also head of the project's steering committee.
 
Thành said the steering committee will convene every month to review the progress of the project.
 
Minister of Transport Nguyễn Văn Thể said the project was on the right track and must not be delayed any further so that it can go into trial operation in early 2025.
 
The deputy prime minister also ordered Đồng Nai’s People’s Committee to complete land clearance and asked the authorities to build road and railway systems connecting the airport with localities.
 
At the next meeting, the transport ministry must report the results of a survey on the road from the airport to HCM City.
 
He also asked members of the Steering Committee to visit the site regularly and push the progress of the project, to make sure it is implemented in accordance with the report.
 
Despite having some positive progress since the site check on April 27 this year, ground levelling work hasn’t been up to expectations, the deputy prime minister said.
 
Transport minister Thể said ground levelling is an important task of the project and will affect other tasks if it is not completed, noting that it must be finished by July next year.
 
He added that a deputy minister has been assigned to the construction site to examine and accelerate the progress.
 
Covering more than 5,580 hectares, the Long Thành International Airport will spread across six communes in Long Thành District. Its construction has been divided into three phases. 
 
In the first phase, a runway and one passenger terminal, along with other supporting facilities, will be built to serve 25 million passengers and 1.2 million tonnes of cargo each year. This phase is scheduled to be completed in 2025.
 
The project started in 2021. Once fully completed in 2050, the airport will be able to handle 100 million passengers and 5 million tonnes of cargo annually.
 
Located 40km to the east of HCM City, the airport is expected to relieve overloading at the southern metropolis’s Tân Sơn Nhất International Airport, which is currently the largest in Việt Nam. VNS
 
Read original article here
 
Newer News
29/07 Private enterprises to be a driving force behind VN's brands
28/07 VIC: Vingroup seeks shareholder approval for business expansion
11/07 HPG: Hòa Phát reported 5 million tonnes in sales during first half of 2025
11/07 Nearly 1,500 household businesses converted into enterprises in six months
07/07 VJC: Vietjet appoints new managing director
07/07 Over 152,000 new businesses enter the market in first half of 2025
02/07 Vietjet launches new Hà Nội–Chengdu route
02/07 HVN: Vietnam Airlines Inaugurates direct Hà Nội–Milan route
30/06 Vinfast inaugurates electric vehicle plant in Hà Tĩnh
24/06 Vietjet launches direct flights connecting Việt Nam and Russia
Older News
15/06 VIC: Automaker VinFast to open more than 50 stores in Europe
15/06 HVN: Vietnam Airlines proposes solutions for recovery
15/06 Việt Nam sees growth in garment exports in first five months
15/06 VNL: Announcement of the change of listing
15/06 REE: Decision on the change of listing
15/06 PDN: RECORD DATE FOR CASH DIVIDEND OF 2021
15/06 NTL: RECORD DATE FOR CASH DIVIDEND OF 2021
15/06 EVG: Notification insider transaction
15/06 LIX: RECORD DATE FOR CASH DIVIDEND OF 2021
15/06 BAF: Decision on the change of listing
 
Newsletter Signup
Top Stories
From pioneer to leader: Việt Nam's stock market hits 25-year milestone
New tax plan could discourage stock investment: insiders
MoF proposes 20% tax on capital gains from securities and equity transfers
HNX halts new stock listings in exchange restructuring
Market begins July with optimism, strong foreign investment
Market Update
Last updated at 12:54:59 PM
VN-INDEX 1,496.46 -6.06/-0.40%
Real-time chart
Top 5 Actives
Top 5 Gainers
Top 5 Losers
My Favorite Quotes
Company Research
Type in the symbol above for thorough background information, key statistics and financial information.
Stock Sectors
We continuously improve our services, here are the latest updates...
Portfolio
Allow you to monitor a customised group of securities. You can set up multiple Portfolios to help you better manage your investments.
Trigger Alerts
Get up-to-date alerts delivered directly to your email address.
Stock Screener
Allow you to filter the market and find exactly what sort of company you are looking for.
Live Terminal
Get instant access to FREE REAL-TIME streaming quotes for hundreds of stocks from HOSE, HNX and UPCOM exchanges.