The disbursed public investment sourced from foreign borrowing was estimated at more than VNĐ9 trillion in the first 11 months of the year, equivalent to only 26 per cent of the plan, an official from the Ministry of Finance said.
In order to improve the disbursement rate of this capital, it was proposed that procedures be further simplified and accountability be enhanced, said Trương Hùng Long, director of the ministry's Debt Management and External Finance Department.
Although the disbursement rate was accelerated in the second half of this year after having achieved a modest rate of just 9 per cent in the year’s first half, Long said that the result was disappointing.
According to the Ministry of Finance, as of November 30, eight out of 13 ministries and agencies proposed lowering the plan of public investment sourced from foreign borrowing by a total of nearly VNĐ3.68 trillion (not excluding VNĐ250 billion of the Ministry of Natural Resource and Environmwnt and VNĐ50 billion of the Ministry of Health which were already approved), and by VNĐ8.8 trillion of 35 out of 59 localities.
The proposed decreased sum totalled more than VNĐ12.4 trillion, or 36.5 per cent of the plan.
Long said that only three ministries and five localities had disbursement rates of more than 50 per cent of the plan, 54 localities and 10 ministries below 50 per cent and notably, six ministries and four localities failed to disburse any public investment sourced from foreign borrowing.
A representative from Hà Nội People’s Committee said that the COVID-19 pandemic in early 2022 affected the implementation of public–invested projects.
Long proposed the Government to issue amendments to Decree No 114/2021/NĐ-CP dated December 16, 2021 about the management and use of official development assistance (ODA) and concessional loans towards further simplifying procedures and enhancing accountability.
Võ Hữu Hiển, the department’s deputy director, said that for public investment sourced from foreign borrowing which failed to be disbursed this year, based on the projects’ implementation progress, ministries, agencies and localities would develop the capital plan for next year if the loan agreements were still valid.
For expired loan agreements, the undisbursed sum would be returned to the lenders and other sources would be arranged to continue to implement the projects.
Hiển pointed out reasons for slow disbursement, such as slow site clearance, problems in bidding procedures and adjustments to projects and loan agreements.
Currently, documents for the disbursement of an estimated sum of VNĐ2.8 trillion were now submitted to the State treasury. If this sum was disbursed, the disbursement rate of public investment sourced from foreign borrowings would be around 34-35 per cent of the plan for the full year.
Overall, the disbursement of public investment from all sources was 58.33 per cent as of the end of November, leaving a huge workload for the remaining days of this year.
Minister of Planning and Investment Nguyễn Chí Dũng said that the disbursement of public investment must be considered a key task to put works into operation and promote socio-economic development.
Ministries, agencies and localities must enhance discipline in the disbursement of public investment, he said, adding that focus must be placed on speeding up site clearance and removing bottlenecks in land and natural resources policies.
Preparations must be geared up to complete investment procedures to ensure readiness and feasibility for early implementation of projects and disbursement of capital from early 2023, he said. — VNS
Read original article here