Dry Cell and Storage Battery Joint Stock Company announces the BOD resolution No.471 dated September 07, 2018 as follows:
- Approving to stop the implementation of project “The land lease in Nhon Trach Textile and Garment Industrial Zone”
- Approving the project “The land lease in An Phuoc Industrial Zone – Dong Nai Province”:
- Project name: The land lease in An Phuoc Industrial Zone – Dong Nai Province
- Location: An Phuoc Industrial Zone, An Phuoc Commune, Long Thanh District, Dong Nai Province.
- Investor: Dry Cell and Storage Battery Joint Stock Company
- Representative: Mr. Tran Thanh Van – CEO
- Land lease area: 8.54 ha
- Lease period: until September 04, 2062 (44 years)
- Total investment capital: VND189,910,203,000 (including VAT 10%)
- Investment funds:
+ Loan: VND120,000,000,000
+ To supplement its working capital: VND69,910,203,000
+ Time of implementation: January 2019.